
In September 1629, the Privy Council made a contract
with Vermuyden, the famous Dutch Drainage Engineer, for the
draining of the Great Level (Bedford Level), the reward for
which was ownership of much of the land. There was a public
outcry against a foreigner receiving recompense of 95,000
acres of English land, and the Commissioners of Sewers, formed
under the Land Drainage Act of 1585, withdrew from the proposal,
but agreed to make contract with Francis, Fourth Earl of Bedford.
The
proposal was to make "Summer Lands", i.e. land fit
for grazing in Summer, but liable to flood in Winter.
In
January 1630, an agreement was made whereby the Earl together
with thirteen Co-Adventurers, including Vermuyden, who was
also engaged as Engineer, should undertake the draining of
the Great Level. Work was commenced in the north of the Great
Level in 1630 and declared complete in 1653, when the Adventurers
took possession of the land. The land remained in the possession
of the Earl until this Century, when it was sold to the tenants.
Around
the turn of the 17th Century, a gradual change was seen to
be taking place in the North Level, with the introduction
of windmills (engines) and horsemills to drain the land. The
provision of "engines" by a landowner was often
prejudicial to other landowners and in three recorded sessions
of the Bedford Level Corporation of 1700, 1701 and 1708, forty
four windmills and thirty seven horsemills were ordered to
be stopped up.
Steam
powered pumps were used for land drainage purposes in Holland
before 1800, and they were soon introduced into this country.
One of the first to be operational was in the North Level
at Sutton St. Edmunds Great Common in about 1820. Incidentally,
Sutton St. Edmunds was one of the first areas in the Country
to have a wind powered pump. By 1828, the River Nene Outfall
had been improved as far as Gunthorpe Sluice (North Level
Main Drain Outfall) and to take advantage of this the Main
Drain and other major drains together with a new outfall sluice
were constructed.
page
top
Tycho
Wing, Agent to the Duke of Bedford, was the main driving force
and he engaged John Rennie to execute the works. Tycho Wing
is commemorated in many local place names, principally Wingland
to the east of the Nene Outfall to the Wash. After the completion
of these works, the clearance level in the Nene was lowered
by ten feet, and the level in the North Level Main Drain by
eight feet. Drainage of the North Level became possible entirely
by gravity. There followed a transformation in the land drainage
of the area and the health of the inhabitants.
Further
improvements were carried out from 1857 to 1862, and 1881
to 1883, in generally lowering and improving the drainage
system. In 1880, Sir John Coode recommended the installation
of steam pumps at Cross Guns, to more effectively drain the
Knarr Lake area, but no works were carried out on the proposal
until 1936, when the North Level Commissioners looking for
more modern standards of drainage, to enable arable farming
to be increased, approved the report by Farran that pumping
stations be erected at Tydd at the main outfall to the Nene,
Cross Guns, Dog-in-a-Doublet and a booster station at French
Drove. These works were commenced in 1938. This system worked
efficiently until on 10th July, 1968 rainfall of 4.15 inches
was recorded at Thorney. At that time, the annual weedcutting
was not completed and hence channel capacity was reduced.
The adverse conditions continued until by September "nil"
soil moisture deficit was recorded at a time when the ground
water table is usually at its lowest. Rainfall continued to
be heavy and field surface flooding occurred and most of the
land was waterlogged. Enormous acreages of crops were lost.
The
previous North Level Commissioners called upon the then Welland
and Nene River Authority Engineer, Harold Clark, to prepare
a report in the improvement of drainage in the North Level.
By entrusting the work to the Welland and Nene River Authority,
a broad approach was possible to safeguard existing drainage
interests on both rivers and utilise the full range of discharge
facilities available.
Clark's
Report was published in 1969, and adopted by the Commissioners
and subsequently the North Level Internal Drainage Board.
Clark
recommended the hiving off of about 5,870 Ha. of the catchment
to the River Welland, to reduce the load on the existing system
and avoid the re-sectioning of the North Level Main Drain,
enlargement of Cross Guns Catchment and the diversion of the
Padholme area and new industrial run-off from Peterborough
to the River Nene near Peterborough together with the pumping
of areas of Tydd and Leverington to the Main Drain.
In
1972, work commenced on the series of improvements proposed
by Clark to bring the land drainage of the 32,000 Ha. of the
North Level up to a standard of 1.40 cubic metres/s/1000 Ha.,
(20 cusec/1000 acres) (equivalent to 0.5 inches of rainfall
in 24 hours).
page
top
At
that time, the North Level area was drained by three pumping
stations, all erected under the 1938 scheme, discharging to
the Nene at Tydd, Cross Guns and Dog-in-a-Doublet, (the latter
two named after pubs). All three stations were overloaded
by present day standards, their capacity being only 0.84 cubic
metres/s/1000 Ha., (12 cusec/1000 acres) and this was reduced
in some cases where the old diesel engines could not be run
at design speed. The channel approach conditions were also
not ideal, being too narrow and hence tending to "starve"
the pumps.
The
arterial drainage channels were constructed to the old design
standard and hence their improvement was also necessary, to
enable them to carry greater design flows. In addition, lower
water levels were needed because of greater design freeboards
and shrinkage of the peat soils.
The
improvement of the North Level Main Drain and New South Eau
feeding it at Cloughs Cross presented a considerable problem,
with a length of 16 miles needing improvement in unstable
soil conditions and the close proximity of public roads, the
cost of re-sectioning would have been prohibitive. The only
sensible solution was to reduce the flow in the channel to
give the design levels with the minimum channel improvements.
To
this end, two areas totalling 5,887 Ha. at the western side
of the area were diverted to the River Welland at Postland
and Newborough by new pumping stations and a reversed arterial
drainage system. Discharge of North Level water to the River
Welland had always been resisted by the River Authority, even
though the Postland and Newborough areas were only a few metres
from the Welland banks. The Authority was concerned that additional
flows in flood times would aggravate the flooding situation
in Deeping Fen and Spalding Town.
However,
improvements to the discharge arrangements to the Welland
Washes at Cowbit and Crowland in 1974 with the construction
of two automatic syphons and restrictions on pumping during
major River floods enabled the Authority to permit the discharge.
Continuing the policy of reducing the load on the Main Drain
System, the Cross Guns Catchment area was increased to 6,640
Ha. from 6,040 Ha., a new station built and the channel works
improved. The new station was completed in 1977, and consists
of six identical pumps, three powered by electricity and three
by diesel, to give at least half capacity during times of
power failure.
page
top
With
the reduction in catchment and the consequential reduction
in discharge, the Main Drain Channel System required minimum
improvement. The Tydd pumping station at the main outfall
to the River Nene had a capacity below the required design
standard, and having been installed in 1938, the plant was
reaching the end of it useful life. However, the cost of renewal
of the plant was very high so the plan at this station was
to install one 3.65 cubic metres capacity electrically powered
pump and electrify two of the diesel pumps to give the old
diesel engines some relief from daily duty, and extend their
life by approximately twenty years. This work being completed
in 1986.
The
expansion of Peterborough to the west of the area presented
a problem with additional surface water run-off from the Eastern
Industrial area of Peterborough. The drainage system was not
designed for this type of discharge, with its high urban peak
flows. The construction of a station to discharge the peak
would also have been expensive, therefore a surface water
storage reservoir was constructed which reduced the peak flow
from 5.7cubic metres/s to 2.0 cubic metres/s. This flow was
pumped to the River Nene via the Padholme Pumping Station,
a 3 cubic metre/s station. An area of 610 Ha. of agricultural
land was also drained to the station which had previously
been in the Dog-in-a-Doublet Catchment. This station is maintained
and operated by the Environment Agency.
The
Dog-in-a-Doublet Old Pumping Station is situated on the River
Nene just downstream of the Dog-in-a-Doublet Sluice, the main
outfall sluice to the River Nene. The station was built on
the site of the lock to the Thorney River which was navigable
at one time to Thorney. The old lock pen is now used as the
outfall to the station, the walls and copings are still visible.
The station has a capacity of 2.2. cumecs and a catchment
area of 2,484 Ha. Constructed in 1938, the station is now
nearing the end of its life. However, due to further development
within the Dog-in-a-Doublet catchment it became clear that
in order to give the developers a 1 in 100 year storm protection
the current pump capacity at the Dog-in-a-Doublet new pumping
station is not going to be adequate. Therefore, the old station
will be refurbished and updated to increase its pump capacity.
The
new automatic pumping station and associated drain improvements
were completed during 1982. There are 2 No. 692mm. dia. and
2 No. 556mm. dia. pumps at the station. The pumps were manufactured
by Sulzer Bros. (U.K.) Ltd. with the larger pumps discharging
1.10cumecs each and the smaller ones 0.70 cumecs each. They
are driven by 140kw and 90kw electric motors respectively.
The station drains a total area of 2484 hectares with a lowest
land level of 0.0m.O.D.N. The maximum design water level at
the station is –1.80m O.D.N. and the High Tide Level
in the adjoining River Nene is + 4.00m O.D.N. i.e. some 5.80
metres higher than the normal maximum pumping level.
page
top
The
freshwater supply from the river Nene to Thorney River and
the land drainage system is provided my means of a single
550mm. Dia. Steel pipeline, with valves and collecting chamber
to control discharge to Thorney River and/or the Middle Drain.
Moving
further north, the Northside area was served by two old pumping
stations at Mouth Lane and Rummers, both discharging to the
River Nene. The Rummers station was an old steam station dated
1864, but was later powered by electricity and diesel, all
the old steam plant has long since disappeared, aothough the
square chimney is still standing.
The
improvement scheme for this area allowed for the abandonment
of the Rummers station and the construction of a new station
at the Mouth Lane site, and the excavation of new or improved
arterial channels to serve a revised catchment area of 1,437
Ha.
The
station contains two similar pumps with a total capacity of
2.0 cubic metres/s. One is powered by diesel power and one
by electricity.
The
Tydd area of 4,789 Ha., situated to the north of the Main
Drain, discharges by gravity direct to that drain. 1,880 Ha.
of the area has suffered from poor drainage due to insufficient
freeboard between land levels and main drain water levels,
and the development close to Shire Drain has prevented improvement
schemes from being carried out on that channel. The improvement
scheme selected, after consideration of several options, was
the construction of the Poplar Pumping Station, to discharge
from the low land to the Main Drain, and the addition of Denhams
Pumping Station to boost the flow in the Shire Drain and avoid
expensive drain works. The remaining 2,909 Ha. drain satisfactorily
to the Main Drain by gravity.
The
Poplar Pumping Station, situated near Tydd Fen Bridge, has
a capacity of 1.6 cubic metres/s., and a catchment area of
1,119 Ha. The booster station (Denhams Pumping Station) has
a capacity of 1.05 cubic metres/s and a catchment area of
761 Ha.
The
last area to be considered was the Leverington area, which
lies south of the Main Drain. Here there are areas of land
with insufficient freeboard, with the existing gravity discharge
and a pumping station has been constructed to lower drainage
levels. Willow Holt Pumping Station has a capacity of 0.82
cumecs and a catchment area of 590 Ha.
The
North Level Area was split into pumped catchment areas served
by either Main River or I.D.B. Pumping Stations and the Welland
and Nene River Authority acted as Consulting Engineers to
the North Level I.D.B. for the design and construction of
all pumping stations, I.D.B. Engineering staff dealing with
arterial drainage improvements.
The
Pumping Stations of Tydd, Mouth Lane, Cross Guns and Dog-in-a-Doublet
received main river grant aid with the North Level I.D.B.
financing the remainder of the cost, the River Authority supplying
design and supervisory staff.
The
I.D.B. Pumping Stations of Poplars, Denhams and Willow Holt
received I.D.B. grant aid with North Level I.D.B. financing
the remainder, W.N.R.A. being paid Consultancy Fees for design
and supervision.
The
North Level I.D.B. are responsible for the running costs,
maintenance and repairs of all stations.
On 10th February 2006 the North Level Internal Drainage Board
and the Westside Marshes Internal Drainage Board were amalgamated
to form the North Level District Internal Drainage Board.
page
top
|